Keep up to date with the latest construction news and project updates for Delano.
Over the last couple of months, all basement and podium slab works have been completed with the above ground structure for each building and townhomes progressing at an impressive rate:
Delano is currently on schedule for completion mid 2025
Exciting progress with the crane installation taking place as scheduled.
Still powering forward in January 2024 with the anchoring works and excavation almost complete. Foundation piles commenced along with detailed excavation of lift pits and pile caps to Buildings A and B. Tower Crane base installed.
Shoring wall piling and capping beam is progressing. The excavation has commenced under Buildings A & B, allowing anchoring works to progress.
The sites security fence has been set up and works are under way with initial ground levelling.