LATEST NEWS

Delano has an estimated completion date of mid 2025

Keep up to date with the latest construction news and project updates for Delano.

July 2024

All basement and podium slab works have been completed

Over the last couple of months, all basement and podium slab works have been completed with the above ground structure for each building and townhomes progressing at an impressive rate:

  • Building A – Level 2 poured and Level 3 formwork
  • Building B – Level 1 poured and Level 2 formwork
  • Buildings C&D – Podium slab poured

Delano is currently on schedule for completion mid 2025

February 2024

Crane installation

Exciting progress with the crane installation taking place as scheduled.

January 2024

Foundation Piles Commenced

Still powering forward in January 2024 with the anchoring works and excavation almost complete. Foundation piles commenced along with detailed excavation of lift pits and pile caps to Buildings A and B. Tower Crane base installed.

September 2023

Excavation commenced

Shoring wall piling and capping beam is progressing. The excavation has commenced under Buildings A & B, allowing anchoring works to progress.

July 2023

Site establishment and works are under way

The sites security fence has been set up and works are under way with initial ground levelling.

GET IN TOUCH
READY TO EXPERIENCE?
Enquire Now